Line efficiency and target
Set the line, the style's minutes and the efficiency you plan on. See the target for each hour, how the line did, and how a new style climbs.
The line
What it made
A new style on the line
Target
93 an hour
748 pieces a day with 30 of 32 operators present, at 65%.
At 100%
144 / h
Efficiency today
67.7%
Against plan
+2.7 pts
The hourly board
What the line should have made by the end of each hour.
| Hour | Target | By then |
|---|---|---|
| 1 | 93 | 93 |
| 2 | 93 | 186 |
| 3 | 93 | 279 |
| 4 | 93 | 372 |
| 5 | 93 | 465 |
| 6 | 93 | 558 |
| 7 | 93 | 651 |
| 8 | 93 | 744 |
A new style, day by day
Efficiency as operators learn it, and the pieces each day.
- Day 135% · 403 pcs
- Day 245.8% · 527 pcs
- Day 354.2% · 624 pcs
- Day 460.2% · 693 pcs
- Day 563.8% · 734 pcs
- Day 665% · 748 pcs
- Day 765% · 748 pcs
- Day 865% · 748 pcs
What this tells you
- Each 5 points of efficiency is about 58 more pieces a day on this line.
- Absence costs 50 pieces today: cross-trained operators keep the bottleneck covered.
- The first six days of a new style make about 3,729 pieces, not the 4,488 a settled line would: plan the ex-factory date with the curve.
Talk to us
Want this on your own styles and orders?
In WOVENN MAKEX the line board updates itself from bundle scans on a phone: this hour against target, the line to walk to first, stoppages timed, and efficiency by operation and operator.
We reply within one working day, starting from the figures you entered here.
In WOVENN MAKEX the line board updates itself from bundle scans on a phone, hour by hour.