Free tool · Time and action

Time and action dates

Tell it when the style must be in store and how it is made. It plans every step back from that date, and says when you must start.

The order

pcs
min

Who makes it, and with what

machines
%

Materials and the way it travels

Processes

Three cases

The normal case makes the date; the worst case would not.

To be in store on 16 May 2027, 20,000 pieces at 12 minutes on 60 machines.

Machines for the normal case

47

Pieces a day, normal

1,240

Sewing days, normal

20

What this tells you

  • Normal case: 55% line efficiency once learnt, 94% of operators present, 5 days to learn the style; 1,240 pieces a day at 12 minutes a piece on 60 machines, 8 hours a day, 6 days a week; 1 fit round, 12 days waiting for a line, material steps at their usual length; 28 days in transit by sea, 5 days to clear and receive.
  • A vendor factory adds about 12 days waiting for a line in the normal case; booking the line with the order shortens it.

The plan, normal case

Each bar is the latest a step can happen and still make the store date. Point at a bar for its dates and float. Outlined bars drive the date.

Dec 26Jan 27Feb 27Mar 27Apr 27May 2723307142128411182518152218152229512192631017
In store 16 May
  1. Tech pack issuedcritical25 Nov
  2. Proto and fit samplecritical26 Nov – 9 Dec
  3. Fit reviewcritical10 Dec – 17 Dec
  4. Fit approvedcritical17 Dec
  5. Costing and quotes8 Dec – 17 Dec
  6. Cost agreedcritical17 Dec
  7. Order issuedcritical17 Dec
  8. Manufacturer confirms the order1 Apr – 5 Apr
  9. Lab dip1 Jan – 8 Jan
  10. Lab dip approved8 Jan
  11. Greige weaving or bookingcritical18 Dec – 9 Jan
  12. Dyeing and finishingcritical11 Jan – 23 Jan
  13. Bulk test and inspectioncritical25 Jan – 29 Jan
  14. Bulk fabric approvedcritical29 Jan
  15. Fabric dispatched to the factory24 Feb – 1 Mar
  16. Fabric in house1 Mar
  17. Book stock trims: Trims22 Feb – 24 Feb
  18. Stock trims dispatched: Trims25 Feb – 4 Mar
  19. Trims in house4 Mar
  20. PP sample in bulk fabriccritical1 Feb – 8 Feb
  21. PP sample reviewcritical9 Feb – 12 Feb
  22. PP sample approvedcritical12 Feb
  23. Size set and PP meetingcritical15 Feb – 4 Mar
  24. Cutting2 Mar – 11 Mar
  25. Embroidery sample24 Feb – 2 Mar
  26. Embroidery sample approved2 Mar
  27. Embroidery (panels)3 Mar – 10 Mar
  28. Sewingcritical5 Mar – 27 Mar
  29. Finishing and packingcritical25 Mar – 7 Apr
  30. Final inspectioncritical8 Apr – 8 Apr
  31. Freight booking6 Apr – 8 Apr
  32. Ex-factorycritical8 Apr
  33. Sea transitcritical9 Apr – 6 May
  34. Clearance and DC receiptcritical7 May – 12 May
  35. Allocation and dispatch to storescritical13 May – 14 May
  36. In storecritical14 May

Talk to us

Want this on your own styles and orders?

In WOVENN every style and order gets this calendar: tasks close themselves as the record moves, partners see their own steps, and when a step slips it shows the best way back.